Passenger traffic on the expressway Budapest-Belgrade line it will be established in a month or two at the most, announced the Prime Minister of Hungary Peter the Hungarian.
That is why the Hungarian Minister of Transport, David Vitezi, will visit Serbia in the coming days and discuss with representatives of the Serbian government the harmonization of signaling and safety systems on the Budapest-Belgrade railway, writes the portal dunaharasztionline.hu, and reports N1.
The mentioned portal emphasizes that the reconstruction of the Hungarian section of the Budapest-Belgrade railway is a project of particular importance for the area, as it directly affects railway traffic on railway number 150, which connects Dunaharašti and several surrounding settlements in the Budapest agglomeration.
When did the work start?
Preparations for the project began in July 2020, while the foundation stone for the Hungarian section was ceremonially laid on October 15, 2021. Construction work began in 2022, and passenger rail traffic on the Budapest-Kelebija section was completely suspended from May 1, 2022.
The contractors left the construction site this spring, and the construction of the railway infrastructure was completed. Freight traffic was established at the end of February, but additional technical and safety conditions need to be met for the start of passenger traffic.
One of the reasons for the delay is the harmonization of the railway signaling and safety systems used in Serbia and Hungary, as well as the completion of the verification of the system planned for application on Hungarian territory.
The former Hungarian Minister of Construction and Transport, Janos Lazar, stated back in December 2025 that the opening of the railway was planned for February 20, 2026. Later it was said that passenger traffic could start between the end of February and March 15, then the deadline was moved to Easter, but that deadline was not met either.
Two tracks were built on the modernized Hungarian section, and the railway was designed for speeds of up to 160 kilometers per hour. According to earlier estimates by Hungarian Railways, the travel time between Budapest and Kelebia could be reduced by 90 minutes, while more direct pairs of trains could run between the two capitals every day.
If the time frame mentioned by Magyar is realized, passenger traffic could start in August or September. However, the official date of the start of traffic has not yet been determined.
The Hungarian announced a review of investments
Previously, after winning the elections, the Hungarian announced that his government had decided to reconsider the investment in the Budapest-Belgrade railway.
He did not provide details, but Minister Vitezi stated that the project was followed by a series of bad decisions from the beginning, from the choice of the route to connect the two capital cities, to the technical solutions due to which the railway designed for 200 kilometers per hour on certain sections will be able to be used at a maximum speed of 160 kilometers per hour, while at the same time multiplying the costs.
Vitezi said that six years ago the project was classified as secret for ten years, and that the Chinese government's opinion is required for its cancellation.
"The Minister of Economic Development and I are responsible for that, and we will initiate a procedure with China to enable the publication of contracts, contract annexes, public procurement documentation and all other data that are publicly available for other state projects," Vitezi said.
Tragedy and suspicion of corruption in Serbia
The Serbian section of the high-speed railway from Belgrade to the border with Hungary was implemented in two phases. The first section from the capital to Novi Sad was put into traffic in March 2022, and from Novi Sad to Subotica in October 2025.
The reconstruction of this railway was accompanied by numerous controversies, especially after the tragedy that occurred on November 1, 2024 at the railway station in Novi Sad, which was renovated as part of this project.